Who it applies to
Buildings on the Department of Urban Development register that are 11 storeys or more above ground and at least 30 years old from the occupancy permit. The 913 figure is the commercial-district priority batch.

913 commercial-district towers on Taipei's register — 11 storeys or more, 30 years or older — must complete their first facade safety filing by 31 December 2026, with New Taipei, Taichung and Kaohsiung drafting comparable rules. This guide brings together Articles 77 and 91 of the Building Act, the Taipei regulations, the cost formula, manual versus drone survey, infrared thermography and the health score — the reference a management committee, property manager or architect needs to decide.
The legal basis sits at three levels. At the top, Article 77(3) of the Building Act requires owners and occupiers to periodically engage professionals recognised by the central building authority to inspect, certify and file. Below that, the Building Public Safety Inspection, Certification and Declaration Regulations govern the certification and filing procedure. Locally, the Taipei City facade safety diagnosis, inspection and declaration regulations require buildings of 11 storeys or more and 30 years or older to be diagnosed by a licensed architect or a practising civil or structural engineer.
The point that matters: none of these mandates exhaustive manual hammer tapping. What the regulation requires is diagnosis and certification by a qualified professional; the choice of method is theirs. The Architecture and Building Research Institute's 2017 study on non-destructive testing of facade tiles using infrared thermography combined with unmanned aircraft found accuracy for tile delamination of around 90% at ambient temperatures of 32–34°C, noting that environmental conditions and instrument angle affect the result.
| Level | Instrument | What it provides |
|---|---|---|
| Primary legislation | Building Act, Article 77(3) | Buildings used by the public must be periodically inspected, certified and filed by professionals recognised by the central building authority, engaged by the owner or occupier. No tool is specified. |
| Primary legislation (penalties) | Building Act, Article 91(1)(4) | Failure to carry out inspection, certification or filing under Article 77(3) and (4) carries a fine of NT$60,000–300,000. Where non-compliance continues past the remedy period, penalties may be repeated and use, water and electricity supply may be suspended or the building closed. |
| Subordinate regulation | Building Public Safety Inspection, Certification and Declaration Regulations | Made by the Ministry of the Interior under Article 77(5), governing the certification procedure, personnel qualifications, report format and filing deadlines. |
| Municipal regulation | Taipei City facade safety diagnosis, inspection and declaration regulations | Applies to buildings on the Department of Urban Development register that are 11 storeys or more above ground and at least 30 years old from the occupancy permit. First filing at 30 years, second at 50, every 10 years thereafter. Diagnostic personnel must be licensed architects or practising civil or structural engineers. |
| Technical literature | Architecture and Building Research Institute, 2017 | Non-destructive testing of facade tiles using infrared thermography combined with unmanned aircraft: 90% accuracy on tile delamination at ambient temperatures of 32–34°C. |
The Taipei Department of Urban Development has listed 913 commercial-district towers of 11 storeys or more, 30 years or older, which must complete a first facade safety diagnosis filing by 31 December 2026. Failure to file carries, under Article 91(1)(4) of the Building Act, a fine of NT$60,000 to NT$300,000. The same article further provides that where non-compliance continues past the remedy period, penalties may be repeated and use suspended, with water and electricity supply cut, the building closed or demolition ordered where necessary.
Against that sit roughly 800 qualified diagnostic personnel nationwide, with over a thousand registered buildings in Taipei alone. As the deadline approaches, availability tightens and pricing follows — committees that arrange early avoid the year-end queue.
Buildings on the Department of Urban Development register that are 11 storeys or more above ground and at least 30 years old from the occupancy permit. The 913 figure is the commercial-district priority batch.
First filing at 30 years, by 31 December of the following year; second at 50 years; every 10 years thereafter. The deadline for the 913-building batch is 31 December 2026.
Failure to file carries a fine of NT$60,000–300,000 under Article 91. Continued non-compliance past the remedy period permits repeated penalties, suspension of use, suspension of water and electricity, or closure.
Manual tapping is precise but expensive, slow, carries fall risk, and leaves its findings largely in one operative's head. Drone survey completes in half a day with no fall exposure, and every defect carries GPS coordinates and quantified data. The decisive difference: manual survey cannot deliver continuous tracking, timeline comparison or trend prediction.
| Dimension | Manual tapping | Drone survey |
|---|---|---|
| Market rate (per m²) | NT$35–1,574 (45× spread) | NT$35/m² on a three-year contract (3 surveys) |
| Duration | 1–2 weeks including scaffolding | Half a day of flying |
| Work-at-height risk | Fall and occupational injury exposure | None |
| Coverage | Limited to what an operative can reach | 70–80% of the full elevation (thermal) |
| Data retention | Paper records and personal experience | Cloud timeline with GPS coordinates |
| Trend tracking | None | Full three-year timeline with automatic alerts |
| Post-typhoon re-survey | Quoted separately | NT$20/m² on a three-year contract |
| Filing compliance | Compliant | Compliant — signed off by the same qualified professionals |
We price per square metre and publish the formula. Three-year contract: NT$35/m² × facade surface area = the total for the term, covering three surveys;single survey without a contract: NT$25/m². Facade surface area means the visible external wall area in m², which can be read from the building permit drawings or confirmed by us during an on-site assessment. Additional surveys within the term are NT$20/m².
| Example | Facade area | Three-year contract | Single survey | Annualised |
|---|---|---|---|---|
| Mid-sized apartment | 800 m² | NT$28,000 | NT$20,000 | NT$9,333 / yr |
| Mid-sized community | 3,000 m² | NT$105,000 | NT$75,000 | NT$35,000 / yr |
| Large community | 7,000 m² | NT$245,000 | NT$175,000 | NT$81,667 / yr |
| Supertall | 15,000 m² | NT$525,000 | NT$375,000 | NT$175,000 / yr |
For comparison: a mid-sized community with 3,000 m² of facade pays roughly NT$150,000–200,000 for one manual whole-building survey, once. The three-year contract is NT$35/m² × 3,000 = NT$105,000 — three surveys across three years, a cloud timeline and health score tracking, averaging NT$35,000 a year. Full breakdown in the 2026 facade survey cost guide.
Each building receives an annual 0–100 score, weighted across five dimensions. Tracked year on year, what you see is a trend rather than a snapshot. Three consecutive years of timeline data is more predictive than one exhaustive survey.
| Dimension | Weight | Why it matters |
|---|---|---|
| Hollowing (pre-detachment) | 40% | The real precursor to a tile falling on someone, and the blind spot manual tapping cannot cover. |
| Cracking | 25% | A structural signal and an entry point for water. |
| Spalling and loss | 15% | Damage that has already happened. |
| Water ingress and mould | 10% | Shortens the building's service life. |
| Surface ageing | 10% | Appearance and warranty considerations. |
The real precursor to a tile detaching is hollowing — an air layer between the tile and the substrate behind it. As the wall sheds heat after sunset, air conducts poorly, so a hollow area cools roughly 0.05–0.5°C more slowly than sound substrate beside it. The DJI Matrice 4T carries VOx 640×512 thermal upscaled to 1280×1024, ±2°C, scanning the full elevation from 10–20 m and finding hollow areas no operative could reach. Per the Architecture and Building Research Institute's 2017 study on non-destructive testing of facade tiles using infrared thermography combined with unmanned aircraft, the method reached 90% accuracy on tile delamination at ambient temperatures of 32–34°C. The study also notes that weather, instrument angle and temperature differential affect interpretation, so calibration is required.
Beyond hollowing, thermography also detects:
The physics in full is in how thermography catches a 0.05°C difference.
An engineer attends to assess conditions, plan the flight path, file the CAA application and confirm ground safety control.
Systematic M4T scanning: panoramic 3D model → visible-light detail → infrared thermal → close capture of suspect areas. Half a day.
The AI processes the full image set, flagging cracking, hollowing, spalling, water ingress and ageing, and computes the 0–100 score.
An inspector recognised by the Department of Urban Development attends, reviews the AI annotations, confirms priority areas and signs off.
A PDF health report in the format required by the Taipei City regulations, usable for statutory filing.
Data is uploaded to the Drone168 platform to build the timeline. The next survey compares automatically, flagging new and worsening defects.
The report can be handed to a qualified inspector or diagnostician for sign-off as it stands. It contains:
Drone facade survey is already a recognised method across major Asian cities. Drone168 is built to the Japanese MLIT model, ready for formal recognition by Taiwan's National Land Management Agency.
The Ministry of Land, Infrastructure and Transport formally recognised drone infrared survey as equivalent to conventional tapping.
Published TR 78:2020, the world's first technical standard for drone facade inspection.
Drones adopted under the Mandatory Building Inspection Scheme, with HK$6bn subsidising 5,000 buildings.
Want to go deeper on one topic? These pieces and service pages fill in the rest.
Most people come here to find out what cleaning costs. But the more important question is: what condition is your facade actually in?
Want to know what condition your facade is in? Start with an asset assessment
Leave your building details and we'll arrange an on-site assessment and walk you through how the health program works